How to Count Cable Tray Fittings from a Layout Drawing: Bends, Tees, Reducers and Risers
To count cable tray fittings from a layout drawing, follow each tray route from start to finish, mark every point where the route turns, splits, changes width or changes level, record the fitting type, angle, width and radius at each point, and then add up identical items into one table. Straight sections, splice plates, bolts, covers and supports are counted alongside. Most quotation problems come from a list that shows only straight lengths, so the supplier has to guess the rest. A clear fitting list makes the quote faster and the delivery more complete. The example numbers in this guide are only illustrations, and allowances should be agreed with your supplier.
Step 1: Know the Fitting Types
Fitting | Where it appears on a drawing | What to record |
Horizontal bend | The route turns left or right in the same plane | Angle (such as 30, 45, 60 or 90 degrees), width, radius |
Vertical inside bend | The route turns up or down, with the bend on the inside of the turn | Angle, width, height, radius |
Vertical outside bend | The route turns up or down, with the bend on the outside of the turn | Angle, width, height, radius |
Tee | One route splits into two | Width of each branch, radius, equal or unequal |
Cross | Two routes cross and connect | Width of each branch, radius |
Reducer | The tray changes width | Width at both ends, and whether it narrows on the left, right or both sides |
Naming varies between suppliers and projects. Some say "elbow" instead of "bend", or "riser" for a vertical bend. In your list, use one naming style and say what each term means, so nothing is misread.
Step 2: Walk Each Route and Mark Every Node
- Pick one tray route and give it a reference, such as a number or letter.
- Start at one end and follow the route on the drawing. At each turn, split, crossing, width change or level change, mark a node and give it a number.
- At every node, write down the fitting type and its details from the table above.
- Check the width on both sides of each node. A width change between two sections must be matched by a reducer or by a different fitting.
- Repeat for the next route, until every route on the drawing has been walked.
Work in one direction on every route, so left and right (for reducers and unequal tees) stay consistent.
Step 3: Count the Straight Sections
- Measure each straight run between nodes along the centerline, not as a direct distance.
- Subtract the length taken up by fittings if the drawing shows them, and divide the remaining length by the standard section length.
- Round up to whole sections, and keep the total by width.
- Add an allowance for cutting and site changes. The allowance depends on the project and the supplier, so agree it in writing rather than assuming a number.
Step 4: Add Joining Parts and Accessories
Item | How it is counted |
Splice plates (connectors) | Per joint, so every joint between a section and a fitting needs a set, as well as joints between sections |
Bolts, nuts and washers | Per splice plate, following the supplier's standard per joint |
Bonding jumpers | At joints where the design requires them, as in the earthing plan |
Hold-down clamps | At supports, by the supplier's method, if the tray type uses them |
Covers and cover clamps | Matching each straight section and fitting that needs a cover |
Hangers, brackets and floor frames | By the support layout, usually a separate list |
End plates | At each open end of a route where one is needed |
Step 5: Build the Counting Table
A simple table keeps everything in one place. The rows below are invented examples to show the format, not a real project.
Route | Node | Item | Angle | Width (mm) | Radius (mm) | Qty | Cover |
R1 | N1 | Horizontal bend | 90 | [example] | [example] | 1 | Yes |
R1 | N2 | Reducer | - | [from] to [to] | - | 1 | Yes |
R2 | N1 | Equal tee | - | [example] | [example] | 1 | Yes |
R2 | N2 | Vertical inside bend | 90 | [example] | [example] | 1 | Yes |
When all routes are done, sort by item, angle, width and radius, and add the quantities of identical lines to make the final list for the RFQ.
Items That Are Often Forgotten
- Fittings at the ends of risers, where a vertical run meets a horizontal one
- Reducers where two different tray widths meet
- Covers for fittings, not just for straight sections
- Splice plates and bolts for every joint on the fittings
- Expansion joints, where the design needs them over long runs
- Supports close to fittings, because loads and joints concentrate there
- Spare fittings that the project wants for later changes
Putting the Result into Your RFQ
- State the tray type (ladder, perforated, solid bottom or other), the material and the finish.
- Give each fitting line with angle, width, radius and quantity, and say whether a cover is included.
- List splice plates, bolts, jumpers, clamps and supports as separate lines, or state that the supplier should include them and show the quantity assumed.
- Attach the drawing and the counting table, and say which one is correct if they ever differ.
- Ask the supplier to point out anything that looks missing or unusual before quoting.
Browse the
cable tray range to see which fittings are offered for each tray type.
Common Mistakes
- Counting only straight sections.
- Forgetting the direction of reducers.
- Missing the radius.
- Counting joints wrongly.
- Leaving out covers on fittings.
- Using different names in the drawing and the list.
- Not checking against the final drawing.
Conclusion
Counting fittings from a drawing is a matter of walking each route, marking every node, recording type, angle, width and radius, and then adding up identical items together with the joints, covers and supports that go with them. A clear table makes the RFQ easier to answer and the delivery easier to check. Agree allowances and terminology with your supplier, and follow your project specification for the final quantities.
FAQ
Do I need to count splice plates separately from fittings?
Yes, or at least state how they are included. Every joint between sections, or between a section and a fitting, needs a set of splice plates and bolts. Ask your supplier whether they are supplied with each fitting or listed separately, so they are not counted twice or missed.
How much extra should I add to the straight section quantity?
It depends on the project, the amount of cutting and the supplier's standard. Agree the allowance with your supplier, and write it into the RFQ, instead of assuming a fixed percentage.
What if my drawing does not show all the fittings?
Count what the drawing shows, mark clearly what you are unsure of, and ask the supplier to review the list before quoting. A short list of questions at the start saves time later, compared with changes after the order.